Skip to content

Military branch Space Force deploys long-awaited Global Positioning System management system following prolonged setbacks

Space Force Officially Takes Command of GPS Next-Gen Control System, OCX, from RTX following prolonged delays.

Space's new GPS control system approved by Space Force, ending years of disruptive postponements
Space's new GPS control system approved by Space Force, ending years of disruptive postponements

Military branch Space Force deploys long-awaited Global Positioning System management system following prolonged setbacks

The GPS Next Generation Operational Control System (OCX) is a significant modernization project for the GPS ground control system, designed to enhance navigation signal accuracy, availability, anti-jamming capability, and secure military signals (M-Code). The journey of OCX began in 2007 with prototyping efforts and prime contract awards in 2010, awarded to Raytheon (now RTX).

History and Development

OCX was intended to replace the legacy Operational Control Segment (OCS) and serve as the backbone control system for the GPS constellation, particularly supporting new GPS Block III and beyond satellites. The program has been divided into multiple phases or "blocks" to incrementally deliver features. Initial contracts and efforts toward OCX started in the late 2000s, with expectations in 2012 that OCX would become operational by 2017.

Delays and Cost Overruns

However, the program has faced significant delays and cost overruns. By June 2016, the program cost projection had risen from an estimated $3.4 billion baseline to over $4.25 billion, triggering a critical Nunn-McCurdy breach, a formal Pentagon breach indicating serious budget and schedule issues. Reasons for the breaches include "inadequate systems engineering at program inception" and the complexity of cybersecurity requirements. Despite these issues, the Department of Defense allowed development to continue after formally certifying the program in late 2016.

By 2025, the total estimated program cost has grown to about $7.7 billion, more than double the original estimate.

Current Status and Future Plans

The U.S. Space Force officially accepted the OCX system from the contractor on July 1, 2025, marking a major milestone after nearly two decades of development. Full operational use of OCX has not yet started; it must pass integrated systems testing and readiness exercises, with operational entry expected by late 2025 or soon after.

The next development phase, called Block 3F, will allow OCX to manage new GPS III Follow-On satellites, with launches starting in 2027. The Space Force requested $70.9 million in 2026 budget for Block 3F to accelerate software development and testing.

Overall, OCX represents a major modernization of GPS ground control capabilities, but its progress has been slowed by technical challenges, cost increases, and schedule slips typical of complex defense software acquisition programs.

Key points:

| Aspect | Detail | |---------------------|-----------------------------------------------------| | Start of development| Prototyping since 2007; prime contract in 2010 | | Expected operational | Initially estimated for 2017 | | Actual acceptance | July 2025 | | Cost overrun | From $3.4B baseline to $7.7B current estimate | | Delay causes | Systems engineering challenges, cybersecurity complexity | | Current status | Accepted but pending full operational deployment; testing ongoing | | Future plans | Block 3F for GPS III Follow-Ons, launches from 2027 |

This history and progression highlight the complexity and scale of upgrading GPS control infrastructure in line with modern cybersecurity, software, and operational requirements. The development of OCX has been a long and arduous road, with former space acquisition executive Frank Calvelli describing it as "troubled," an "albatross," and a "problem child." Modern software practices favor breaking down development work into manageable "sprints" and making rapid, iterative updates. However, the scale and complexity of the OCX project caused the delays. The Air Force initially estimated that OCX would enter operations by June 2017 with a program cost of $3.7 billion, according to the Government Accountability Office. It took eight years for RTX to deliver Blocks 1 and 2, which enable command and control of the satellites. The Space Force officially operates the GPS OCX, and the update is key to enabling enhancements like anti-jamming, improved accuracy, and secure geolocation using M-Code. Col. Stephen Hobbs, commander of Mission Delta 31, stated that OCX will enter operations late this year, if all goes well. Delays and extra costs had mounted so much by 2016 that the Air Force had to declare a Nunn-McCurdy breach, indicating "critical" cost and schedule overruns. Trying to create an entirely new, large software system all at once is now viewed as an outdated approach.

  1. The U.S. Air Force initially started the development of the GPS Next Generation Operational Control System (OCX) in 2007, with the prime contract awarded to Raytheon in 2010.
  2. Despite initial expectations that the OCX would become operational by 2017, significant delays and cost overruns occurred, leading to a formal Pentagon breach in 2016, indicating serious budget and schedule issues.
  3. By 2025, the total estimated program cost for the OCX had grown to about $7.7 billion, more than double the original estimate, highlighting the complexity and scale of upgrading GPS control infrastructure.
  4. The U.S. Space Force officially accepted the OCX system in 2025, marking a major milestone, and future plans include the Block 3F development phase, which will allow OCX to manage new GPS III Follow-On satellites, with launches starting in 2027.

Read also:

    Latest